2019-2020 Watermain Looping Project: Weather permitting, the contractor, GM Contracting, Inc., is scheduled to begin locating utilities October 2, 2019 and may possibly start pipe installation on 598th Avenue towards the end of the week. According to the contractor, this will only require the west shoulder of 598th to be closed on the south end. Barricades will likely be put up the following week. Residents along the project will have access. The contractor anticipates little to no inconvenience to residents this week. More information will be made available once the contractor has provided the City with actual dates that the barricades will be set up for road closure. Please contact jbromeland@eaglelakemn.com with any questions or concerns. Check back for project updates.

Tentative Project Schedule (Subject to Change)

Start Project: 10/02/19

Find Existing Utilities along 598th Ave: 10/02/19 - 10/04/19

Installation of new utilities along 598th Ave: 10/07/19 - 10-18-19

Close 598th Ave and set up detour: 10/10/19 - 10/31/19

Road Closure Map

Connect utilities along 598th Ave: 10/14/19 - 10/23/19

Installation of new utilities behind city hall: 10/21/19 - 10/23/19

Connect utilities along 598th Ave: 10/23/19 - 10/25/19

Restoration: 10/21/19 - 10/31/19


2019 Linda Drive Drainage Improvements Project: Weather permitting, the contractor, Bromeling Excavating, Inc., is scheduled to begin on Monday, September 30, 2019 impacting the Linda Drive, Linda Court, and Linda Circle properties that are part of the 2019 Linda Drive Drainage Improvements Project. The contractor will start at LeSueur Avenue and work northward. Residents are asked to temporarily park vehicles on the street across from the construction areas. Driveway restoration will occur shortly after the underground drains have been constructed. When possible, the contractor will provide temporary access to driveways between constructing the underground drains and restoring driveway aprons. All work within the City's right-of-way is expected to be complete on or before November 1, 2019.

The City thanks you in advance for your patience and cooperation during the projects.